Cap Metro Achieves PTC Milestone

PTC

By Dave Dech, VP of Rail Operations

Capital Metro has been working to put in place a positive train control (PTC) system along the 32-mile MetroRail line. We have now met an important threshold by completing all of the statutory requirements to qualify for an extension to the federally mandated deadline of Dec. 31.

PTC is a technological upgrade of the nation’s rail lines designed to create an additional layer of safety to rail. Congress mandated the improvements back in 2009 and gave rail operators until the end of this year to implement PTC.

The good thing is that Capital Metro has met all of the statutory requirements, which enables us to request the extension. Essentially, that means we’ve demonstrated sufficient progress on the project to convince the government that we’re on our way to full implementation. The Federal Railroad Administration is now reviewing our request, and we expect to receive notice of approval within 90 days. Until then, Capital Metro will continue to operate and continue work on PTC implementation. That means that customers will still occasionally experience disruptions to MetroRail service during this work.

Cap Metro is among many rail operators across the country to request this extension, including Caltrain in the San Francisco Bay area and New Jersey Transit. It allows the agency another two years to fully implement the PTC system, a goal that we are committed to reaching.

New Rail Schedule Rolls Out March 19

Rail-Schedule_3-19-2018

Capital Metro will put in place a new MetroRail schedule next week for evaluation. We’ll operate on this new schedule beginning the week of March 19 and evaluate how the service performs. The new schedule was developed in response to recent service disruptions on the MetroRail Red Line.

 

Please refer to these schedules, beginning March 19:

The agency is currently working on two major construction projects along the 32-mile rail line. These projects are an investment in the future of MetroRail, and will pay off with doubled frequency and capacity. Capital Metro is building additional passing points along the MetroRail route that will enable the service — once the new Downtown Station is completed — to double its frequency and capacity. The other project is implementing a federally mandated positive train control system, which will ensure the long-term safety and security of the service.

The projects will continue throughout 2018, and some service disruptions can be expected for the remainder of the year. During the week of March 19, though, we will evaluate the new schedule, which should minimize service disruptions. To ensure the transition will be seamless, routes for rail connector buses have been adjusted as well.